Sunday, 24 June 2012

The countdown

Well we rushed around and sorted out the mortgage so we are ready for settlement> Was going to happen Monday but now Thursday.

Top soil was delivered and spread out on Saturday.

The paint touch ups and other fixes should be done tomorrow/Tuesday. Final inspection on Thursday hopefully and a handover of the keys!

We noticed a cracked tile on the front porch yesterday and also one of the pipes connecting the rain water tank has been a massive hole in it (think the landscaper has done it), so I guess that will be something to get fixed once we are moved in as I doubt it would be fixed before Thursday.

Our current house is filled with boxes as we packed the remaining things today with enough to get us through the week.

Also busy organising fence quotes. Good news is the vacant block next to us said to send through the quote we go with and they will organise their 50% (this is Eden Brae). House behind is rented so need to chase up the owners. Hopefully there are no delays with them.

Hoping to start the moving process on Saturday and get everything moved over to our new home :)

5 more days!

Sunday, 3 June 2012

The landscaping has started

Seems like everything is in slow motion at the moment... Driveway has been down for about 2 weeks and still has not been coloured (painted), assuming it is painted as we thought it was coloured concrete when it was laid. Colour is suppose to be Cova Bluestone...

Landscaping has started. Site has been cleared of rubbish and scraped and levelled. It looks so different with the fencing down. Actually looks like a house and not a work site any more.

On another plus we did notice our carpet has been laid over the past few days. Not alot left to do. Can't wait to move in that is for sure!

Driveway

Exercise sign out the front

Sunday, 6 May 2012

The main tiling

The tilers were back last week. When we went past saw them putting in some long hours. The main tiling - living/dining/kitchen/entry is all done now. Looks great.

The bathrooms look like they are all complete too. Towel rails, toilet roll holders, toilets, etc all done.

The door handles are on all the doors too, so last week was a busy week.

Now waiting on glass splashback in the kitchen, carpet, driveway and landscaping. Fingers cross the driveway is started this week.

Peeking through the window

Pillars and tiling done

Entry tiled

Monday, 30 April 2012

The electrician is back

The painters finished painting last week. Must say it looks pretty good.

The kitchen benchtop was installed on Friday along with the bathroom benchtops and sinks. Shower screens were installed too. The wardrobes have been fitted with the shelves and rails too :)

Today the electrician has been back to install the light switches and power points.

Hopefully the bath, toilets and bathroom accessories are installed this week and maybe the tilers back to finish off the living area.

Will not be much left to do. Door handles, carpet, flyscreens, kitchen splashback... That should finish off the inside then.

Driveway was meant to be started last week but still nothing.

It is getting closer that is for sure and we can not wait to move!


Tuesday, 3 April 2012

The kitchen

The kitchen cupboards and island have been installed. It was delivered yesterday and the cupboards had been put together and today they had all been put in their place :)

Ensuite cupboards have also been put together and are sitting in the bedroom. Not sure if the main bathroom has been done as we can not see in.

Kitchen looks great. Can't wait to see the glass splashback as we have not seen the colour of it yet and also can't wait to see the ceaser stone bench.

Hopefully the tiling will start once the kitchen is finished. Tiling was suppose to start yesterday but I guess with the kitchen coming late it delayed them. Another step closer.

Wednesday, 21 March 2012

The lockout

We are officially locked out... Garage door is on and the front and laundry doors are on, locking us out of our house. So now we have to peer through the windows :)

The internal doors have started to be put up and the electricals are being cut out.

Gyprock is finished, cornices finished and skirting boards are all done too.

Next week should see the kitchen started. Then I guess the bathrooms and tiling will start?!

Garage door


Monday, 12 March 2012

The gyprock

They have started gyprocking the walls and ceilings. Should be all finished this week. Then next week start waterproofing the wet areas. The house is already starting to take shape inside with some of the walls in and parts of the roof. Can't wait to see the progress made in the coming week.

The brick cleaners finished cleaning the bricks last week. The eaves were completed and the downpipes were all done too.

Insulation also started last week, so they were pretty busy last week at the house.


Monday, 5 March 2012

The electricals

Bit of an update since the roof started. We finally saw some nice weather and the roof was finished rather quickly. Looks great. Site has been cleaned up too.

The 2nd column out the front was finally finished off just in time for the brick cleaning to start. The brick cleaning started last week, just the sides of the house to be finished now.

The electricals/telephone line have been roughed in.

Just waiting for the brick cleaning to finish and the outside will almost be done. Everything for the eaves is on site but with this weather it isn't helping. Hopefully they can get to that this week to get us to lock up?

Also spoke to the builders who are building the house behind us and they are doing colorbond fencing so that was good news.

Our whirly bird

Roof done



Clean bricks




Friday, 24 February 2012

The roof

The roof has finally started! After all this beautiful weather during the week I think they worked on the house for about 2 days! 1 day putting up the rest of the steel supports in the roof and another putting half of the roof on. Still waiting on the bricklayers to come back to finish out the front...

All starting to take shape. Be good once the roof is done so we don't rely on the weather.

Friday, 17 February 2012

The gutters and fascia

Bricks are 99% done. They still have to do one of the pillars at the front. Thought it would have been done today, looks like next week now.

The gutters and fascia were done today. The outside is really starting to take shape now. Roof is due to be done next week and is on site ready to go. Sarking is there too. Wonder if the roofers work Saturdays?






Saturday, 11 February 2012

The bricklaying has started

Well finally with some clear skies and the rain holding off for a few days the bricklayers have managed to return to the house to start bricklaying. Looks like they have made some good progress given they have only been there I think about 2 days!

Side wall of the garage is done and part of the wall on the media room and a few rows around the back of the house.

The brick colour looks great with the off white mortar and the bricklayers are doing a great job. Hoping this rain stays away all next week so they can return and really get stuck into it.

Garage

Alfresco wall

Back of house

Monday, 30 January 2012

The bricks

As promised our bricks were delivered today. We were keen to see the colour as the sample we got when we went to Boral looked totally different to what we saw at the colour selection and the colour on the website. So we were pleased to see the colour looked better than we thought. The sand for the bricks should be delivered tomorrow and hopefully the bricklayers start on Wednesday.




Tuesday, 24 January 2012

The windows

Drove past the house today and to our surprise the windows were in! The plumbing had been done as well. Bricks should be delivered by the weekend.






Friday, 20 January 2012

The frame continues

Another drive by the 'house' to see what the builders got up to today and was very pleased to see the roof had gone up.

Doesn't look like there is much steel left on the ground. The frame for the desk in the children's activity room still needs to go in but other than that I couldn't see what else was left to do?

Not sure if they will be there tomorrow to finish up? If nothing is done tomorrow then Monday should see the windows in, yay!

Few more photos from today's progress.

Such a great street presence with the high pitched roof.

Our roof is so tall it hides the house behind. Love the high pitched roof!


Lots of steel. Looks so clean and straight!


Thursday, 19 January 2012

The frame has started

Frame started yesterday. Looks like everything but the roof had been done except for a few bits and pieces. Went past today and part of the roof has been done and the beams for the alfresco area.

It is starting to take shape and it looks great.








Tuesday, 17 January 2012

The Windows

Drove past today thinking that the frame would have been started since it was not raining today, but nothing. Frame has been moved around the site a bit and sorted out by the looks of it. Windows and doors have been delivered too.

The colours of the windows and doors look pretty good. The colour is Bradnams Ultra Silver.

Also noticed that they have drawn on the slab where the frame will go.

Fingers crossed we the frame started tomorrow.







Wednesday, 11 January 2012

The frame

The frame was delivered today just like we were told it would be. Also had a call from Peter our site supervisor today. He said they should start putting the frame up next Monday.

The termite protection was laid on Monday as well. The site has also been cleaned up and scraped the land more to tidy it up.

Can't wait to see the frame up!!!






Saturday, 17 December 2011

The slab

Yay, we have a slab down! Was laid on Wednesday. Still looking a bit wet. Now looking forward to seeing a frame delivered (just like every next step in the build!)

Certainly looks different with a slab down and is good to make out the rooms and get a better feel for the house.