Sunday 6 May 2012

The main tiling

The tilers were back last week. When we went past saw them putting in some long hours. The main tiling - living/dining/kitchen/entry is all done now. Looks great.

The bathrooms look like they are all complete too. Towel rails, toilet roll holders, toilets, etc all done.

The door handles are on all the doors too, so last week was a busy week.

Now waiting on glass splashback in the kitchen, carpet, driveway and landscaping. Fingers cross the driveway is started this week.

Peeking through the window

Pillars and tiling done

Entry tiled

No comments:

Post a Comment