Well we rushed around and sorted out the mortgage so we are ready for settlement> Was going to happen Monday but now Thursday.
Top soil was delivered and spread out on Saturday.
The paint touch ups and other fixes should be done tomorrow/Tuesday. Final inspection on Thursday hopefully and a handover of the keys!
We noticed a cracked tile on the front porch yesterday and also one of the pipes connecting the rain water tank has been a massive hole in it (think the landscaper has done it), so I guess that will be something to get fixed once we are moved in as I doubt it would be fixed before Thursday.
Our current house is filled with boxes as we packed the remaining things today with enough to get us through the week.
Also busy organising fence quotes. Good news is the vacant block next to us said to send through the quote we go with and they will organise their 50% (this is Eden Brae). House behind is rented so need to chase up the owners. Hopefully there are no delays with them.
Hoping to start the moving process on Saturday and get everything moved over to our new home :)
5 more days!
Follow our progress as we build our first home the Havana One by McDonald Jones Homes@Glenmore Ridge.
Showing posts with label Balinese Resort Facade. Show all posts
Showing posts with label Balinese Resort Facade. Show all posts
Sunday, 24 June 2012
Sunday, 3 June 2012
The landscaping has started
Seems like everything is in slow motion at the moment... Driveway has been down for about 2 weeks and still has not been coloured (painted), assuming it is painted as we thought it was coloured concrete when it was laid. Colour is suppose to be Cova Bluestone...
Landscaping has started. Site has been cleared of rubbish and scraped and levelled. It looks so different with the fencing down. Actually looks like a house and not a work site any more.
On another plus we did notice our carpet has been laid over the past few days. Not alot left to do. Can't wait to move in that is for sure!
Landscaping has started. Site has been cleared of rubbish and scraped and levelled. It looks so different with the fencing down. Actually looks like a house and not a work site any more.
On another plus we did notice our carpet has been laid over the past few days. Not alot left to do. Can't wait to move in that is for sure!
Driveway |
![]() |
Exercise sign out the front |
Thursday, 17 May 2012
The driveway
Been a while since I have updated the blog.
The driveway has been laid today. Couldn't see much as it was dark when we went past. House looks like it has been cleaned also.
We also have our gas meter. We have had the standard oyster lights installed which we didn't realise we were getting. Good for now and will replace them once we get a chance.
Also had our glass kitchen splashback installed which looks great.
When looking around the house it looks like someone has tried to get in through one of the windows in the living area... Not impressed. They have bent all the window frame. See what happens about that.
Landscaping is to start next week.
The driveway has been laid today. Couldn't see much as it was dark when we went past. House looks like it has been cleaned also.
We also have our gas meter. We have had the standard oyster lights installed which we didn't realise we were getting. Good for now and will replace them once we get a chance.
Also had our glass kitchen splashback installed which looks great.
When looking around the house it looks like someone has tried to get in through one of the windows in the living area... Not impressed. They have bent all the window frame. See what happens about that.
Landscaping is to start next week.
Tuesday, 17 April 2012
The painters
The painters have started. Hard to see how much they have done, but looks like the first coat has been done.
Wednesday, 11 April 2012
The tiling
Laundry, bathroom and ensuite have been fully tiled. Bathroom vanities are in place and the laundry tub has been installed too. The front porch has also been tiled, which was a nice surprise as we weren't sure if it was being tiled as we were going to use merbau to build a front deck. Now we don't have to worry straight away as the front porch looks good being tiled. One less thing to worry about.
SS said painters will be in this week or next to start painting. Must be getting closer now.
SS said painters will be in this week or next to start painting. Must be getting closer now.
Wednesday, 21 March 2012
The lockout
We are officially locked out... Garage door is on and the front and laundry doors are on, locking us out of our house. So now we have to peer through the windows :)
The internal doors have started to be put up and the electricals are being cut out.
Gyprock is finished, cornices finished and skirting boards are all done too.
Next week should see the kitchen started. Then I guess the bathrooms and tiling will start?!
The internal doors have started to be put up and the electricals are being cut out.
Gyprock is finished, cornices finished and skirting boards are all done too.
Next week should see the kitchen started. Then I guess the bathrooms and tiling will start?!
Garage door |
Monday, 5 March 2012
The electricals
Bit of an update since the roof started. We finally saw some nice weather and the roof was finished rather quickly. Looks great. Site has been cleaned up too.
The 2nd column out the front was finally finished off just in time for the brick cleaning to start. The brick cleaning started last week, just the sides of the house to be finished now.
The electricals/telephone line have been roughed in.
Just waiting for the brick cleaning to finish and the outside will almost be done. Everything for the eaves is on site but with this weather it isn't helping. Hopefully they can get to that this week to get us to lock up?
Also spoke to the builders who are building the house behind us and they are doing colorbond fencing so that was good news.
The 2nd column out the front was finally finished off just in time for the brick cleaning to start. The brick cleaning started last week, just the sides of the house to be finished now.
The electricals/telephone line have been roughed in.
Just waiting for the brick cleaning to finish and the outside will almost be done. Everything for the eaves is on site but with this weather it isn't helping. Hopefully they can get to that this week to get us to lock up?
Also spoke to the builders who are building the house behind us and they are doing colorbond fencing so that was good news.
Our whirly bird |
Roof done |
![]() |
Clean bricks |
Friday, 17 February 2012
The gutters and fascia
Bricks are 99% done. They still have to do one of the pillars at the front. Thought it would have been done today, looks like next week now.
The gutters and fascia were done today. The outside is really starting to take shape now. Roof is due to be done next week and is on site ready to go. Sarking is there too. Wonder if the roofers work Saturdays?
The gutters and fascia were done today. The outside is really starting to take shape now. Roof is due to be done next week and is on site ready to go. Sarking is there too. Wonder if the roofers work Saturdays?
Saturday, 11 February 2012
The bricklaying has started
Well finally with some clear skies and the rain holding off for a few days the bricklayers have managed to return to the house to start bricklaying. Looks like they have made some good progress given they have only been there I think about 2 days!
Side wall of the garage is done and part of the wall on the media room and a few rows around the back of the house.
The brick colour looks great with the off white mortar and the bricklayers are doing a great job. Hoping this rain stays away all next week so they can return and really get stuck into it.
Side wall of the garage is done and part of the wall on the media room and a few rows around the back of the house.
The brick colour looks great with the off white mortar and the bricklayers are doing a great job. Hoping this rain stays away all next week so they can return and really get stuck into it.
Garage |
![]() |
Alfresco wall |
Back of house |
Tuesday, 24 January 2012
The windows
Drove past the house today and to our surprise the windows were in! The plumbing had been done as well. Bricks should be delivered by the weekend.
Friday, 20 January 2012
The frame continues
Another drive by the 'house' to see what the builders got up to today and was very pleased to see the roof had gone up.
Doesn't look like there is much steel left on the ground. The frame for the desk in the children's activity room still needs to go in but other than that I couldn't see what else was left to do?
Not sure if they will be there tomorrow to finish up? If nothing is done tomorrow then Monday should see the windows in, yay!
Few more photos from today's progress.
Doesn't look like there is much steel left on the ground. The frame for the desk in the children's activity room still needs to go in but other than that I couldn't see what else was left to do?
Not sure if they will be there tomorrow to finish up? If nothing is done tomorrow then Monday should see the windows in, yay!
Few more photos from today's progress.
Such a great street presence with the high pitched roof. |
Our roof is so tall it hides the house behind. Love the high pitched roof! |
Lots of steel. Looks so clean and straight! |
Thursday, 19 January 2012
The frame has started
Frame started yesterday. Looks like everything but the roof had been done except for a few bits and pieces. Went past today and part of the roof has been done and the beams for the alfresco area.
It is starting to take shape and it looks great.
It is starting to take shape and it looks great.
Monday, 5 December 2011
The formwork and piering
Well another drive by today and the form work is done and the piering as well :) Step by step getting closer to a slab!
Thursday, 22 September 2011
Subscribe to: